Image of back arrow Back to filtered results

XRN 5565
Appointment of CDSP as the Scheme Administrator for the Energy Price Guarantee (EPG) for Domestic Gas Consumers (Gas) (UNC0824)

Last Updated
10 Nov 2023
Status
Implemented
Release Type
Ad-hoc
Implementation Date
31 Mar 2023
Proposer NGN Impacted DSC service area

Customer Change Team Leader uklink@xoserve.com

Summary

The Government has proposed the EPG (Gas) Scheme, for domestic customers, to secure reductions in the energy bills of domestic customers within Great Britain. The intention is for the Central Data Service Provider (CDSP) to perform the function of the EPG (Gas) Scheme (the ‘Scheme’) Administrator and that the scheme to be implemented by 1st October 2022.

Modification 0824 confirms the role of the CDSP as the Scheme Administrator for the EPG (Gas) and gives them the relevant powers to make changes under the DSC in order to facilitate implementation and administration of this Scheme, from 1st October 2022, in line with the Government direction.

This change proposal seeks to design, build and implement the relevant functionality and processes in order for the CDSP to fulfil its role as the Scheme Administrator.

Impacted Customer Types

  • Shipper
  • Supplier

Documents

Document title Comment Last updated CHMC outcome
Change Proposal Presented for approval at eChMC 27/09/22  28/09/22 Approved at eChMC 27/09/22
Initial Review Stage not required N/A N/A
High Level Solution Options Stage not required N/A N/A
Solution Review Stage not required N/A N/A
Detailed Design Stage not required N/A N/A
Evaluation Quotation Reports (EQR) Stage not required N/A N/A
Business Evaluation Reports (BER) Presented to ChMC 07/12/2022 05/01/23 ChMC approved BER
Change Completion Reports (CCR) N/A 10/11/23 Approved at ChMC 08/11/2023

Timeline

Initial Review
Change Proposal Raised 28/09/22
Status Verbal update to eChMC 27/09/2022
Capture
CP will continue into Capture 12/10/22
Status Presented for information at ChMC
Solution Consultation
Expected: 00/00/00
Status Stage not required
Awaiting Delivery
Expected: 00/00/00
Status Stage not required
In Delivery
Expected: 13/12/22
Status Approved straight into Delivery
Implemented
Change has been delivered 31/03/23
Status Delivered