XRN 5561
Reform of Gas Demand Side Response (DSR) Arrangements (Modification 0822)

Last Updated
16 Nov 2022
Status
Implemented
Release Type
Ad-hoc
Implementation Date
17 Oct 2022
Proposer National Grid Impacted DSC service area

TBC

To be confirmed

Customer Change Team Leader uklink@xoserve.com

Summary

The current Gas Demand Side Response (DSR) framework has been in place since 2016 and the DSR market has only opened once since then, which was during Beast from the East in 2018. Zero bids were placed onto the DSR Market within the OCM.

As part of our winter preparedness activities, we have reviewed the current DSR framework and engaged with our customers and stakeholders to understand the reasons for the lack of participation and if there are any reforms that could be made which would make the make the scheme more attractive.

In order to have a guaranteed level of response, we are proposing to hold an Invitation to Offer process where shippers will be invited to post DSR offers and if they are accepted, Shippers will receive an “Option” payment. The receipt of the Option Payment obligates Shippers to post an offer on to the DSR market in the event of it opening following either the issuing of a Gas Balancing Notification (GBN) or a Margins Notice (MN) at D-1.

Therefore, we are proposing the following reforms:

  • Introduction of an “Option” or Availability payment
  • Introduction of additional penalty charges for Shippers who do not post bids onto the DSR market in accordance with the “business rules” as per UNC modification 0822

Impacted Customer Types

  • NGT
  • Shipper
  • DNO

Documents

Document title Comment Last updated CHMC outcome
Change Proposal Approved into Capture at ChMC  12/09/2022 Approved into Capture 07/09/2022
Initial Review Stage not required N/A N/A
High Level Solution Options Stage not required N/A N/A
Solution Review Due to the nature of the change, the solution option and detail design are being presented together N/A N/A
Detailed Design 3098.6- RT - PO 15/11/2022 Presented for awareness at ChMC 09/11/2022
Evaluation Quotation Reports (EQR) Stage not required N/A N/A
Business Evaluation Reports (BER) Approved 16/11/2022 Approved at ChMC 09/11/2022
Change Completion Reports (CCR) Approved 16/11/2022 Approved at ChMC 09/11/2022

Timeline

Initial Review
Change Proposal Raised 07/09/22
Status Change awaiting approval to capture at ChMC
Capture
Approved into Capture 07/09/22
Status ChMC approved into Capture
Solution Consultation
Expected: 00/00/00
Status Stage not required
Awaiting Delivery
Expected: 00/00/00
Status Stage not required
In Delivery
Solution option and detail design phases issued together 17/10/22
Status Detailed Design issued for awareness. Presented for information at ChMC 09/11/2022
Implemented
Implemented 17/10/22
Status Delivered 17/10/2022