Last Updated
|
29 Apr 2024 |
Status
|
Implemented
|
Release Type
|
Unallocated |
Implementation Date
|
27
Apr
2024
|
Proposer | Xoserve | Impacted DSC service area |
N/A Not applicable |
Customer Change Team Leader | uklink@xoserve.com |
Summary
The current CMS system will be rebuilt (the scope being the same contact codes as current CMS with the addition of a new contact code for Supplier theft (SUT). The new solution will take into account customer pain points and reduce customer effort where possible. The system solution will be built, funded and owned by Correla and charged to Xoserve through subscription charges, therefore eliminating the need for DSC customers to source up front investment funding |
XRN 5556A
New CMS Version 1
Implemented |
This XRN covers the first release of two contact codes (Shipper MNC - found meters, and SUT - Supplier raised theft). MNC's have historically been managed off line and this release will allow customers to raise MNC's through a standard on line porta...
|
XRN 5556B
New CMS - Version 1.1
Implemented |
This XRN will be a child XRN to 5556 and covers the Duplications Process (DUP), minor enhancements to the UI of the new system and the set to Extinct new process.
|
XRN 5556C
CMS Rebuild Version 1.2
Implemented |
For the new CMS system there is a requirement to bulk upload multiple contacts within CMS
This child XRN will deliver the functionality of uploading multiple contacts via a new file, as processes are migrated over to new CMS from legacy CMS they will...
|
XRN 5556D
CMS Rebuild Version 1.3
Implemented |
This XRN will be a child XRN to 5556 and covers the Isolations (ISO) and Dead to Live (DTL) processes with minor enhancements to the UI of the new system.
|
XRN 5556E
CMS Rebuild Version 1.4
Implemented |
This XRN will be a child XRN to 5556. Within this version we will strive to deliver additional functionality and processes where possible, however our priority processes are Address amendments (ADD/UNC). Should we have capacity in this version releas...
|
XRN 5556F
CMS Rebuild Version 1.5
Implemented |
This XRN will be a child XRN to 5556. Within this version we will strive to deliver additional functionality and processes where possible, however our priority processes are RFA (Request for Financial Adjustment) and CDQ (Consumption Dispute Query) S...
|
XRN 5556G
CMS Rebuild Version 1.6
Implemented |
Update:
As part of CHMC in November it was agreed that the CMS update versions would be taken out of the Change proposals that we have raised to ensure that should we reprioritise delivery the version releases can remain in a sequential manner.
The V...
|
XRN 5556H
CMS Rebuild – Delivery of GSR and MUS
Implemented |
This XRN will be a child XRN to 5556. Within this version we will strive to deliver additional functionality and processes where possible, however our priority processes are Gas Safety Regulations (GSR), Manage Unregistered Sites (MUS). Should we hav...
|
XRN 5556I
CMS Rebuild – Delivery of XRN5604 and XRN5605
Implemented |
Within this version we will strive to deliver additional functionality and processes where possible, however our priority processes are Shipper Agreed Reads (SAR) and Key Meter Issue (KMI). Should we have capacity in this version release to include a...
|
XRN 5556J
CMS Rebuild Version - Delivery of Must Reads
Implemented |
This XRN will be a child XRN to 5556. Within this version we will strive to deliver additional functionality and processes where possible, however our priority processes will be the Must Reads Process (MUR). Should we have capacity in this version re...
|
XRN 5556K
CMS Rebuild Version - Delivery of DMQ and Generic Workflows
Implemented |
DMQ has now been launched in the new CMS on 08 April, as 5556.K contains both DMQ and GEN, the latter will be delivered on the weekend of 27/04/24. After which this XRN will be marked as implemented.
Within this version we will strive to deliver addi...
|
Impacted Customer Types
- GT
- IGT
- NGT
- Shipper
- DNO
Documents
Document title | Comment | Last updated | CHMC outcome |
---|---|---|---|
Change Proposal | N/A | 12/09/2022 | CP was presented for information at ChMC 07/09/2022 |
Change Pack Standard of Service Query Management | 3098.5 - RT - PO | 19/10/2022 | In consultation / ChMC approval period |