Last Updated
|
17 Jul 2024 |
Status
|
Current
|
Release Type
|
Unallocated |
Implementation Date
|
TBC
|
Proposer | Xoserve | Impacted DSC service area |
N/A Not applicable |
Customer Change Team Leader | uklink@xoserve.com |
Summary
In Release 3 (August to September 2024), we intend to progress the DDP changes to existing dashboards for XRN5615 (Mod819 Class 4 Vacant Sites), in readiness for the 8th November agreed release date.
The team will be working on backend source to target designs and configurations for the dashboard updates, in addition to developing and testing the changes to the affected dashboards.
Completion of this work and development of new dashboards will continue into Release 4 with the deployment of the changes and updates taking place in line with the XRN5615 release date.
Impacted Customer Types
- Other
- IGT
Documents
Document title | Comment | Last updated | CHMC outcome |
---|---|---|---|
Change Proposal | Presented to ChMC for information 10/07/24 | 01/07/2024 | N/A |
Initial Review | Stage not yet reached | N/A | |
High Level Solution Options | Stage not yet reached | N/A | |
Solution Review | Stage not yet reached | N/A | |
Detailed Design | Stage not yet reached | N/A | |
Evaluation Quotation Reports (EQR) | Stage not yet reached | N/A | |
Business Evaluation Reports (BER) | Stage not yet reached | N/A | |
Change Completion Reports (CCR) | Stage not yet reached | N/A |
Timeline
Contact the Change Team
Need to get in touch with a member of the Change Team?