Last Updated
|
30 Oct 2025 |
Status
|
Current
|
|
Release Type
|
Ad-hoc |
Implementation Date
|
TBC
|
| Proposer | Cadent | Impacted DSC service area |
|
| Customer Change Team Leader | uklink@xoserve.com |
Summary
DNs want the CDSP to provide a new, centralised Emergency Contact Validation Service to improve the quality of, and confidence in, the EMR data held on CDSP systems.
This change will create a new DSC Service that incorporates the following elements:
Datasets:
· Early April-26 the CDSP will ask the DNs to confirm their specific requirements and then collate individual LDZ datasets;
· DNs will validate and confirm datasets by end of April-26;
· The supply meter points included in this exercise will predominantly be the top 200 sites in each LDZ (by AQ);
· A top-up’ of sites just outside of the top 200 may be required to ensure each LDZ has 200 sites;
· All 13 LDZs will be included in the exercise;
EMR Contacts, Call Handling and Validation:
· Call handling exercise is anticipated to be held May-August26;
· The CDSP will ring the emergency contacts (ECs) (up to five) for each site and determine whether the details are PASS or FAIL;
· Calls will be scripted in line with current DN scripts;
· A reason for a PASS or FAIL result must be logged.
· Whether sufficient emergency contacts are recorded should also be noted. (UNC TPD Q 2.3.2).
· Initial delivery of the call handling service is expected to occur between May-Aug 2026 and then annually thereafter.
CDSP Management Reporting:
· Interim reporting will be conducted at the end of each month during the call handling period. ie. May, June, July & August;
· Reports will be sent to relevant DNs and Shippers;
· If Shippers send in updated ECs between reports, this will be recorded against the EC;
· Reporting is timed ahead of planned NEC/DNs industry exercise to test emergency response procedures which is usually conducted in October;
· Follow-up reports will be run quarterly at end of November26 and February27.
Out of scope:
o DN obtained emergency contact data not held in UK Link;
o Provision of reports to DESNEZ or Ofgem.
Impacted Customer Types
- Shipper
- DNO
Documents
| Document title | Comment | Last updated | CHMC outcome |
|---|---|---|---|
| Change Proposal | Change Proposal Raised | 30/10/25 | Awaiting approval |
| Initial Review | Stage not yet reached | N/A | |
| High Level Solution Options | Stage not yet reached | N/A | |
| Solution Review | Stage not yet reached | N/A | |
| Detailed Design | Stage not yet reached | N/A | |
| Evaluation Quotation Reports (EQR) | Stage not yet reached | N/A | |
| Business Evaluation Reports (BER) | Stage not yet reached | N/A | |
| Change Completion Reports (CCR) | Stage not yet reached | N/A |
Timeline
Contact the Change Team
Need to get in touch with a member of the Change Team?
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.