XRN 5858
DDP Release 5 2024/2025

Last Updated
11 Dec 2024
Status
Current
Release Type
Ad-hoc
Implementation Date
31 Jan 2025
Proposer Xoserve Impacted DSC service area

N/A

Not applicable

Customer Change Team Leader uklink@xoserve.com

Summary

Following prioritisation discussions at ChMC, in release/sprint 5 (December 2024 to January 2025), we intend to continue with the DDP changes to: 

 

DN’s – DN Invoice Forecast 

  • Creating a report for tracking December snapshot potential costs through to April so DNs are aware of any fluctuations. 
  • Adding new Charge Type Code 'ZCO' filter into global filter of charging simulation dashboard. 
  • Adding overall percentage differences in the charging simulation summary report. 
  • (Stretch) Create report showing meter point level calculation for supply points that have individually calculated charge types. 

 

Shippers – Shipper Pack 

  • Create a view of read rejection reasons so that shippers can compare their performance with the industry. 
  • Create a report so shippers can view the number of meter points that have an incorrect meter read factor and / or units’ definition in their portfolio for the previous month including a 12-month trend. 
  • (Stretch) Create a report showing monthly industry must read performance totals as a percentage and as a 12-month trend. 

 

IGTs – IGT Reads 

  • Create a Quick Reference feature to look up Rejection Codes, as well as trend analysis on Rejection Reasons 
  • (Stretch) Create a view to help the IGTs understand the read rejection reasons where meter points have not been consistently read. 

Impacted Customer Types

  • Shipper
  • DNO
  • IGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal Change Proposal Raised 28/11/24

ChMC approved scope 11/12/2024

Change Completion Reports (CCR) Stage not yet reached   N/A

Timeline

Change Proposal raised
28/11/24
Status Awaiting ChMC approval
Change development
28/11/24
Status Stage not required
Solution development
28/11/24
Status Stage not required
Detailed design
28/11/24
Status Stage not required
Awaiting delivery
28/11/24
Status Stage not required
In delivery
28/11/24
Status Change approved into delivery
Change implemented

Contact the Change Team

Need to get in touch with a member of the Change Team?

You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.