XRN 5846
New allowable value (M - Thermal Mass) for Meter Type Code (H100)

This XRN is part of XRN 5868 June 25 Major Release
Last Updated
13 Mar 2025
Status
Current
Release Type
Major
Implementation Date
27 Jun 2025
Proposer Xoserve Impacted DSC service area

Customer Change Team Leader uklink@xoserve.com

Summary

We need to ensure that the allowable value for meter types includes thermal mass meters for all Metering and RGMA flows coming in and out of UK link.

Impacted Customer Types

  • Shipper
  • DNO
  • IGT
  • NGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal Awaiting Approval at ChMC on 13/11/24 13/11/24 CP approved at ChMC 13/11/24
Solution Review Stage not required    
Detailed Design 3342.1. VO - PO 20/02/2025 Approved 12/03/2025
Evaluation Quotation Reports (EQR) Stage not required   N/A
Revised Business Evaluation Reports (BER) Approved 13/03/2025 Approved 12/03/2025
Change Completion Reports (CCR) Stage not yet reached   N/A

Timeline

Change Proposal raised
30/10/24
Status Awaiting ChMC Approval 13/11/24
Change development
30/10/24
Status CP Approved at ChMC 13/11/24
Solution development
30/10/24
Status Stage not required
Detail Design Change Pack issued
17/02/25
Status Consultation closes out on 03/03/25
Awaiting delivery
30/10/24
Status Stage not required
In delivery
12/03/25
Status Design Change Pack and BER approved at ChMC 12/03/2025
Change implemented