XRN 5784
Modification 0862 Amendments to the current Unidentified Gas Reconciliation Period arrangements

This XRN is part of XRN 5868 June 25 Major Release
Last Updated
31 Dec 2024
Status
Current
Release Type
Major
Implementation Date
TBC
Proposer SEFE Energy Impacted DSC service area

Service Area 10 (Current Apr 21)

Invoicing Customers

Customer Change Team Leader uklink@xoserve.com

Summary

This Change Proposal has been raised to deliver the requirements outlined in Modification 0862 Amendments to the current Unidentified Gas Reconciliation Period arrangements.

Modification 0862 seeks to amend the UIG Reconciliation Period so that UIG is reconciled in the same month/s that the energy originated from. UIG Reconciliation should cover the whole month or months wherein the energy was consumed. Reconciliation must not be limited to the exact dates that the energy originated from. UIG Reconciliation should continue to be reconciled back to Line in the Sand to ensure that no UIG is unaccounted for.

It is not the intention of this Modification to amend any other meter point reconciliation calculations and all other processes associated with UIG reconciliation are to remain the same.

Impacted Customer Types

  • Shipper
  • DNO
  • NGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal CP Raised 14/05/2024 ChMC approved on 08/05/2024 
DSG Discussion  DSG Meeting 20/5/24 14/06/2024  
Initial Review Not required   N/A
High Level Solution Options Stage not yet reached   N/A
Solution Review Stage not yet reached   N/A
Detailed Design 3321 - LO - PO 18/11/24 ChMC approved 11/12/2024
Evaluation Quotation Reports (EQR) Stage not yet reached   N/A
Business Evaluation Reports (BER) Stage not yet reached   N/A
Change Completion Reports (CCR) Stage not yet reached   N/A

Timeline

Change Proposal raised
24/04/24
Status Awaiting ChMC approval
Change development
08/05/24
Status Approved into development
Solution development
24/04/24
Detailed design
Detailed Design Change Pack Issued 18/11/24
Status Design approved at ChMC 11/12/24
Awaiting delivery
24/04/24
Status Awaiting June 25 scope approval in January ChMC
In delivery
Change implemented