XRN 5556F
CMS Rebuild Version 1.5

This XRN is part of XRN 5556 CMS Rebuild parent XRN
Last Updated
06 Nov 2023
Status
Implemented
Release Type
Ad-hoc
Implementation Date
06 Nov 2023
Proposer Xoserve Impacted DSC service area

N/A

Not applicable

Customer Change Team Leader uklink@xoserve.com

Summary

This XRN will be a child XRN to 5556. Within this version we will strive to deliver additional functionality and processes where possible, however our priority processes are RFA (Request for Financial Adjustment) and CDQ (Consumption Dispute Query) Should we have capacity in this version release to include anything additional, this shall be communicated out via Change Packs and the forums ChMC, CoMC and the Customer Focus Group.

Impacted Customer Types

  • Shipper
  • DNO
  • IGT

Documents

Document title Comment Last updated CHMC outcome
Change Proposal CP raised 31/03/2023 For information at ChMC 12/04/2023
DSG Discussion N/A 26/06/2023 N/A

Detailed Design

3174.3 - VO - PO

14/07/2023

Deferred by ChMC 09/06/23, Detailed Design to be re-issued in June Change Packs for voting at July ChMC

Detailed Design

3184.2 - VO - PO

14/07/2023

Re-issued Detailed Design approved at ChMC 12/07/23

Timeline

Initial Review
CP raised 31/03/23
Status For information at ChMC 12/04/23
Capture
Expected: 00/00/00
Status Stage not required
Solution Consultation
Expected: 00/00/00
Status Stage not required
Awaiting Delivery
Detail Design Change Pack re- issued 12/06/23
Status Detailed Design deferred, to re-issued in June Change Packs
In Delivery
Detailed Design Change Pack re-issued 12/06/23
Status ChMC approved Detailed Design 12/07/23
Implemented
Expected: 06/11/23
Status Successfully implemented