XRN 5556E
CMS Rebuild Version 1.4
                    
                                This XRN is part of XRN 5556 CMS Rebuild parent XRN
                            
                    | 
                                        Last Updated
                                     | 18 Aug 2023 | 
                                        Status
                                     | 
                                        Implemented
                                     | 
| 
                                        Release Type
                                     | Ad-hoc | 
                                        Implementation Date
                                     | 
                                            14
                                            Aug
                                            2023
                                         | 
| Proposer | Xoserve | Impacted DSC service area | N/A Not applicable | 
| Customer Change Team Leader | uklink@xoserve.com | 
Summary
This XRN will be a child XRN to 5556. Within this version we will strive to deliver additional functionality and processes where possible, however our priority processes are Address amendments (ADD/UNC). Should we have capacity in this version release to include anything additional, this shall be communicated out via Change Packs and the forums ChMC, CoMC and the Customer Focus Group.
Impacted Customer Types
- Shipper
- DNO
- IGT
- NGT
Documents
| Document title | Comment | Last updated | CHMC outcome | 
|---|---|---|---|
| Change Proposal | CP raised | 31/03/2023 | For information at ChMC 12/04/2023 | 
| DSG Discussion | N/A | 03/07/2023 | N/A | 
| Detailed Design | 3174.2 - VO - PO | 15/05/2023 | ChMC approved Detailed Design 09/06/2023 | 
Timeline
Initial Review
                                        
                                            CP raised
                                                31/03/23
                                        
                                        
                                            Status
                                            For information at ChMC 12/04/2023
                                        
                                Capture
                                        
                                            Expected:
                                                00/00/00
                                        
                                        
                                            Status
                                            Stage not required
                                        
                                Solution Consultation
                                        
                                            Expected:
                                                00/00/00
                                        
                                        
                                            Status
                                            Stage not required
                                        
                                Awaiting Delivery
                                        
                                            Detail Design Change Pack issued
                                                15/05/23
                                        
                                        
                                            Status
                                            ChMC approved Detailed Design 09/06/23
                                        
                                In Delivery
                                        
                                            Expected:
                                                00/00/00
                                        
                                        
                                            Status
                                            Awaiting
                                        
                                Implemented
                                        
                                            Delivered
                                                14/08/23
                                        
                                        
                                            Status
                                            Implementation successful
                                        
                                Contact the Change Team
Need to get in touch with a member of the Change Team? 
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.