Last Updated
|
14 Nov 2022 |
Status
|
Implemented
|
Release Type
|
Ad-hoc |
Implementation Date
|
16
Sep
2022
|
Proposer | Xoserve | Impacted DSC service area |
Service Area 4 (Current Apr 21) Meter Read/Asset processing |
Customer Change Team Leader | uklink@xoserve.com |
Summary
This change seeks to enhance the reconciliation process for Prime & Sub sites within the CDSP central systems to remove the need for manual monitoring and data correction. Delivery of this change proposal will address the problem scenarios as defined within the problem statement.
As the required changes will be internal to the CDSP and the analysis and corrective action is being undertaken in a support and maintenance capacity the proposed release will be ad hoc, in line with other maintenance work, to deliver benefits immediately.
Impacted Customer Types
- Shipper
Documents
Document title | Comment | Last updated | CHMC outcome |
---|---|---|---|
Change Proposal | Change Proposal Raised | 04/01/22 | Approved into Capture at ChMC on 12/01/2022 |
Initial Review | Stage not required | N/A | N/A |
DSG Discussion | N/A | 24/01/2022 | N/A |
High Level Solution Options | Stage not required | N/A | N/A |
Solution Review | Stage not required | N/A | N/A |
Detailed Design | 2955.6-MT-PO | 22/02/2022 | Approved at ChMC on 09/02/2022 |
Evaluation Quotation Reports (EQR) | Stage not required | N/A | N/A |
Business Evaluation Reports (BER) | Stage not required | N/A | N/A |
Change Completion Reports (CCR) | N/A | 14/11/2022 | Approved at ChMC 09/11/2022 |