Last Updated
|
11 Sep 2020 |
Status
|
Implemented
|
Release Type
|
Minor |
Implementation Date
|
04
Jul
2020
|
Proposer | CDSP | Impacted DSC service area |
N/A Not applicable |
Customer Change Team Leader | uklink@xoserve.com |
Summary
Minor Release Drop 7 delivery is focused on 2 External changes and 1 Internal Change that need to be implemented by the end of May 2020.
The 2 external changes that have been identified for Minor Release Drop 7 are:
XRN5036 - Updates to must read process – please note this change was de-scoped from Nov-20 (XRN5110)
XRN5065 - Addition of Email Address to DES Last Accessed Report
The 1 internal change identified for Minor Release drop 7 is:
XRN4989 - To implement the online solution for the Credit Interest process as per the UKLink requirements – Associated defect – 1063
Minor Release Drop 7 was successfully implemented on the 4th July 2020.
Impacted Customer Types
- IGT
- Shipper
- DNO
Documents
Document title | Last updated | Type |
---|---|---|
XRN5152 CCR | 11/Sep/2020 | |
XRN5152 CP | 03/Sep/2020 |
Timeline
Contact the Change Team
Need to get in touch with a member of the Change Team?
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.