This CP is the Parent Change Request for June 2020 Major Release, Scope includes the following Changes:
XRN 4772
Composite Weather Variable (CWV) Improvements
Implemented |
This Change is in scope of June 2020 Release.
Modification 0659 is working to add into the UNC two new data items to improve the accuracy of the Composite Weather Variable (CWV) – this XRN is seeking to create the mechanism in which the solar radiati...
|
XRN 4865
Amendment to Treatment and Reporting of CYCL Reads
Implemented |
This Change is in scope of June 2020 Release.
An issue has been identified with the estimated read created for the confirmation effective date (CED) for class 3 and 4 meter points in the case where the asset is installed for a date prior to the confi...
|
XRN 4930
Requirement to inform Shipper of Meter Link Code Change
Implemented |
This Change is in scope of June 2020 Release.
Pre-Nexus implementation, when a Meter Link Code was amended, a K15 record was sent to the Shipper within an MRI file. A shipper has identified that this is no longer happening and is reliant on these upd...
|
XRN 4850
Notification of Customer Contact Details to Transporters
Implemented |
This Change is in scope of June 2020 Release.
This change has two elements and ultimately aims to improve communications with end consumers during planned and unplanned gas supply disruptions.
The first element involves the implementation of a proc...
|
XRN 4888
Removing Duplicate Address Update Validation for IGT Supply Meter Points via Contact Management Service (CMS)
Implemented |
This Change is in scope of June 2020 Release.
The current duplicate address validation performed within Contact Management Service (CMS) was not designed with a full understanding of IGT address management processes, particularly those associated to ...
|
XRN 4932
Improvements to the quality of the Conversion Factor values held on the Supply Point Register (MOD0681S)
Implemented |
This Change is in scope of June 2020 Release.
Mod 0681 seeks to introduce the CDSP being given the authority to make changes to the conversion factor in the following circumstances only:
a) where the AQ of a meter point falls to 732,000 kWh or lower,...
|
Impacted Customer Types
- IGT
- Shipper
- DNO
Documents
Document title | Last updated | Type |
---|---|---|
CCR for June 20 | 17/Mar/2021 | |
BER for XRN4996 June 20 | 04/Nov/2020 | |
EQR for June 2020 Release | 12/Aug/2019 | |
XRN4996 - Jun-20 Release Delivery | 12/Aug/2019 |
Timeline
Contact the Change Team
Need to get in touch with a member of the Change Team?
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.