Last Updated
|
18 Feb 2019 |
Status
|
Implemented
|
Release Type
|
Minor |
Implementation Date
|
16
Feb
2019
|
Proposer | Npower | Impacted DSC service area |
Service Area 6 (Previous Dec 18 – Mar 21) Annual quantity, DM supply point capacity and offtake rate reviews |
Customer Change Team Leader | uklink@xoserve.com |
Summary
Where an actual read is submitted following an estimated transfer reading, if the Actual reading is less than the estimated reading a negative volumes is created (the actual read validates to the last Actual read recorded so the period last actual to estimated transfer read would be a positive value). In the instances where the estimated transfer reading and the Actual read are the only reads considered for the AQ Calculation the AQ will be re-calculated to 1, if other reads are considered within the optimum or sub-optimum period for the AQ Calculation the AQ may still be incorrectly calculated resulting in a reduced AQ.
Impacted Customer Types
- Shipper
Documents
Document title | Last updated | Type |
---|---|---|
BER For MiR Drop 3 XRN4690 & XRN4717 | 15/Mar/2019 | |
XRN4690 CP | 15/Jan/2019 | |
XRN4690 - High Level System Solution | 15/Jan/2019 |
Timeline
Contact the Change Team
Need to get in touch with a member of the Change Team?
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.