Image of back arrow Back to filtered results

XRN 5246
Confirmation File (.CNF) Processing Capacity Improvement

This XRN is part of XRN 5371 Minor Release Drop 10
Last Updated
13 Jul 2021
Status
Implemented
Release Type
Minor
Implementation Date
04 Sep 2021
Proposer CDSP Impacted DSC service area

Service Area 1 (Previous Dec 18 – Mar 21)

Manage Supply Point Registration

Customer Change Team Leader uklink@xoserve.com

Summary

A POC has been completed to the processing jobs in UK Link to tune the processing job sufficiently to double the effective capacity, therefore allowing higher volumes of transactions to be completed within one day

 

Further work is required to complete a full impact analysis of the effects this increase might cause – both to the file flows directly associated with the confirmation, but equally on other related downstream activity, such as the provision of meter reads, AQ calculations, Gemini and Invoicing.

 

Following successful analysis, an assessment can be made as to the benefit value and appetite for changes to be commissioned.

Impacted Customer Types

  • IGT
  • Shipper
  • DNO

Documents

Document title Last updated Type
XRN5246 CP 13/Jul/2021 PDF

Timeline

Initial Review
Start: 07/10/20
Status This was approved to proceed into Capture at Change Management Committee 07/08/2020
Capture
Expected: 00/00/00
Status Awaiting
Solution Consultation
Change Pack Issued 14/06/21
Status Change Pack issued, solution in consultation until 28/06/2021
Awaiting Delivery
Solution approved at ChMC 07/07/21
Status Awaiting release assignment
In Delivery
Expected: 00/00/00
Status Awaiting
Implemented
Implemented on 4th September 2021 04/09/21
Status Implemented as part of Minor Release Drop 10

Contact the Change Team

Need to get in touch with a member of the Change Team?

You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.