Summary
A POC has been completed to the processing jobs in UK Link to tune the processing job sufficiently to double the effective capacity, therefore allowing higher volumes of transactions to be completed within one day
Further work is required to complete a full impact analysis of the effects this increase might cause – both to the file flows directly associated with the confirmation, but equally on other related downstream activity, such as the provision of meter reads, AQ calculations, Gemini and Invoicing.
Following successful analysis, an assessment can be made as to the benefit value and appetite for changes to be commissioned.
Impacted Customer Types
- IGT
- Shipper
- DNO
Documents
Document title | Last updated | Type |
---|---|---|
XRN5246 CP | 13/Jul/2021 |
Timeline
Contact the Change Team
Need to get in touch with a member of the Change Team?
You can email us at: uklink@xoserve.com and we'll get back on the same day between the hours of 9:00am to 4:30pm.