Change Pack February 2023
3139 - VO - PO - Change Pack February 2023
3139.1 - VO - PO - XRN 5579A - Long Term flow Swap Automation Change Pack - Detailed Design
This Change Pack is out for a 10 working day consultation. We invite the industry to review the information and provide any responses. At the ChMC meeting in March, we will seek approval for the change.
3139.1 - VO - PO - XRN 5579A - Long Term flow Swap Automation Change Pack - Detailed Design
updated 04/04/23
Start Date:
13th February 2023
Consultation end date:
27th February 2023
3139.2 - VO - PO - XRN 5606 MOD 813 - For Representation
This Change Pack is out for a 10 working day consultation. We invite the industry to review the information and provide any responses. At the ChMC meeting in March, we will seek approval for the change.
3139.2 - VO - PO - XRN 5606 MOD 813 - For Representation
updated 22/03/23
Start Date:
13th February 2023
Consultation end date:
27th February 2023
3139.3 - VO - PO - XRN 5547 - Updating the Comprehensive Invoice Master List and INV Template - Solution Review
This Change Pack is out for a 10 working day consultation. We invite the industry to review the information and provide any responses. At the ChMC meeting in March, we will seek approval for the change.
3139.3 - VO - PO - XRN 5547 - Updating the Comprehensive Invoice Master List and INV Template - Solution Review
updated 22/03/23
Start Date:
13th February 2023
Consultation end date:
27th February 2023
3139.4 - VO - PO - XRN5379 - Class 1 read service Procurement Excercise MOD 0710 - Transitional arrangements - For Information
This Change Pack is for information only; however, if you want to put forward any comments or questions, then please use the response form. This Change Pack is open for 10 working days, if you do wish to comment.
3139.4 - VO - PO - XRN5379 - Class 1 read service Procurement Excercise MOD 0710 - Transitional arrangements - For Information
updated 22/03/23
Start Date:
13th February 2023
Consultation end date:
27th February 2023
3139.5 - VO - PO - XRN 5535A - Processing of CSS Switch Requests Received in ‘Time Period 5’ - Detailed Design
This Change Pack is out for a 10 working day consultation. We invite the industry to review the information and provide any responses. At the ChMC meeting in March, we will seek approval for the change.
3139.5 - VO - PO - XRN 5535A - Processing of CSS Switch Requests Received in ‘Time Period 5’ - Detailed Design
updated 22/03/23
Start Date:
13th February 2023
Consultation end date:
27th February 2023
3139.6 - VO - PO - XRN 5556D - CMS Rebuild version 1.3 - Detailed Design
This Change Pack is out for a 10 working day consultation. We invite the industry to review the information and provide any responses. At the ChMC meeting in March, we will seek approval for the change.
3139.6 - VO - PO - XRN 5556D - CMS Rebuild version 1.3 - Detailed Design
updated 22/03/23
Start Date:
13th February 2023
Consultation end date:
27th February 2023